Project Number: P00011092
Budget: $120 million
Schedule:
- Construction Start: Summer 2018
- Estimated Construction Completion: Fall 2020
Square Feet:
-
- 62,000 gross sq. ft. addition
- 159,600 gross sq. ft. renovation
Design Team: Ballinger
Construction Team: Walbridge Aldinger
Maps and Construction Logistics
Central Campus, Medical Center and Ross Athletic Campus Core Map
Design
Perspective from North University Avenue and South Thayer Street
News
Regents Approve Design for Kraus Renovation
October 19, 2017
Major Renovations Planned for Historic Kraus Building
September 15, 2016