Project List by Building
Does not include projects being done by individual units and third-party university agents.
1100 North University Building
Building # 1000188 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022093 | Fire Pump Replacement | Construction Documents | 04/21/2025 | 05/09/2025 |
7300 W Joy Road
Building # 1005506 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022412 | Dexter Pharmacy Consolidation | Bid-Award | 01/27/2025 | 05/16/2025 |
Aero Eng Lab Pumping Station
Building # 1000423 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022898 | Room 1001 Air Compressor and Chiller | Construction Documents | 01/13/2025 | 05/16/2025 |
Alumni Memorial Hall
Building # 1000151 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022509 | Smoke Detector Replacements | Construction Documents | 05/20/2024 | |
P00023235 | Stone Veneer Structural Bracket Replacements | Construction Documents | 05/26/2025 | 08/15/2025 |
Angell James B Hall and Tisch Hall
Building # 1000152 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021906 | Angell Hall Roof Replacement | Construction | 05/05/2025 | 08/22/2025 |
P00021917 | Angell James B Hall and Tisch Hall Comprehensive Studies Program Renovation | Construction | 09/03/2024 | 05/23/2025 |
Ann Street Parking Structure
Building # 1005132 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022782 | 2025 Concrete & Waterproofing Repairs | Construction Documents | 05/05/2025 | 09/30/2025 |
Art Architecture Building
Building # 1000432 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022459 | Room 2115 Classroom Renovation | Substantial Completion | 08/01/2024 | 08/23/2024 |
P00023032 | 1114T to Gender inclusive Restroom | Construction Documents | 05/05/2025 | 07/25/2025 |
BLOCK-0000009
Building # 0000009 - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021929 | NC65 Parking Lot Reconstruction | Bid-Award | 05/01/2025 | 08/22/2025 |
BLOCK-0000014
Building # 0000014 - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021930 | M69 Parking Lot Reconstruction | Bid-Award | 05/01/2025 | 08/22/2025 |
BLOCK-0000022
Building # 0000022 - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021971 | BLOCK-0000022 Palmer Commons - LSI Plaza Paving Repairs 2024 | Construction | 06/07/2024 | 11/29/2024 |
BLOCK-0000031
Building # 0000031 - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022096 | North University Pedestrian Traffic Signal | Construction | 09/09/2024 | 01/10/2025 |
BLOCK-0000102
Building # 0000102 - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020776 | NCRC Biorepository Exterior Liquid Nitrogen Feed Line Replacement | Bid-Award | 04/08/2024 | 01/31/2025 |
BLOCK-0000118
Building # 0000118 - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021932 | M75 (West) Parking Lot Reconstruction | Schematic Design | 05/01/2026 | 08/14/2026 |
BLOCK-0000125
Building # 0000125 - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022779 | Northwood V Primary Switchgear Ugrade | Schematic Design | 09/22/2025 | 03/11/2027 |
Bagnoud Francois-Xavier Building
Building # 1000395 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021485 | Fire Alarm Panel Replacement | Construction | 10/02/2023 | 11/28/2024 |
Blau Jeff T Hall
Building # 1005370 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022425 | Room 4560B and 4560E Additional Cooling | Substantial Completion | 07/15/2024 | 10/04/2024 |
Brehm Tower
Building # 1005102 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020476 | KEC CSPD Equipment Replacement | Construction | 10/29/2024 | 01/29/2025 |
P00022516 | Brehm Chilled Water Optimization | Construction Documents | 04/14/2025 | 01/22/2026 |
Brighton Center For Specialty Care
Building # 1005239 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021978 | FY25 BCSC Renovations for New Services (OTO and Facial Cosmetic Services) | Construction | 08/19/2024 | 01/09/2025 |
Brown George Granger Memorial Laboratories
Building # 1000407 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020118 | GG Brown Machine Shop | Substantial Completion | 09/02/2022 | 05/31/2023 |
P00021324 | Renovate Suite 2316 and Misc Rooms | Construction | 08/28/2023 | 11/17/2023 |
P00021646 | Room 2231 Lab Renovations | Construction | 01/15/2024 | 04/12/2024 |
P00021647 | Room 2271 Lab Renovations | Construction | 02/12/2024 | 06/07/2024 |
P00021851 | ECM - HPS Boiler DeCx | Construction | 06/04/2024 | 08/02/2024 |
P00022454 | Room 2166 Office Furniture | Construction Documents | 07/01/2024 | 08/30/2024 |
Bursley Joseph A & Marguerite K Hall
Building # 1000555 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021676 | Bursley Joseph A & Marguerite K Hall Roof Replacement | Construction | 05/05/2025 | 08/15/2025 |
P00022396 | ECM- Kitchen DX Compressors | Construction Documents | 01/21/2025 | 03/31/2025 |
Burton Memorial Tower
Building # 1000155 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00014928 | Window Replacement | Bid-Award | 05/05/2025 | 08/29/2025 |
Business Admin Executive Dorm
Building # 1000139 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020414 | Ross School of Business Executive Dormitory and Sam Wyly Hall Renovations | Construction Documents | 01/13/2025 | 11/30/2026 |
Campus Safety Services Building
Building # 1000742 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022340 | EHS Suite 1500 | Construction Documents | 10/21/2024 | 12/20/2024 |
P00022688 | Room 1510 Kitchenette Renovation | Construction Documents |
Chemistry & Dow Willard H Laboratory
Building # 1000158 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00015484 | Chemistry Building and Willard H. Dow Laboratory East Campus Switching Station Upgrade | Construction | 06/06/2022 | 12/27/2024 |
P00021566 | Renovate Labs 4613 and 4615 | Substantial Completion | 06/03/2024 | 11/25/2024 |
P00023128 | Renovate labs 4225 4217 and 4215 | Schematic Design | 05/26/2025 | 10/31/2025 |
P00023256 | Heating Hot Water Coil Replacement | Construction Documents | 08/04/2025 | 10/31/2025 |
Church St Parking Structure
Building # 1000257 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00023293 | Elevators #1 & #2 Replacements | Schematic Design | 05/04/2026 | 11/18/2026 |
Climate and Space Research Building
Building # 1000441 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022709 | Elevator #2 Partial Renovation | Bid-Award | 05/19/2025 | 07/30/2025 |
P00022795 | Replace Boiler Feedwater System | Construction Documents | 06/30/2025 | 08/29/2025 |
P00023043 | Partial Roof Replacement | Construction Documents | 05/05/2025 | 08/15/2025 |
Cook William W Legal Research Library
Building # 1000184 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00018717 | Cook William W Legal Research Library Remediate Leaks at Smith Underground Addition | Bid-Award | 08/11/2025 | 11/30/2025 |
P00019749 | Replace Domestic Water Booster Pump in Room 154 | Construction Documents | 04/07/2025 | 06/06/2025 |
P00022657 | Cook Legal - Hutchins Hall - SSWB LED Bulb Replacement Project | Construction | 09/02/2024 | 02/14/2025 |
Cooley Mortimer E Building
Building # 1000403 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00023284 | Fire Alarm Upgrade | Construction Documents | 10/13/2025 | 05/08/2026 |
Dana Samuel Trask Building
Building # 1000189 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021160 | Rooms 3046 & 3066 Studio | Construction Documents |
Dearborn Administration Bldg
Building # 1001012 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00023170 | Relocation of College of Education Health and Human Services | Schematic Design | 05/12/2025 | 11/14/2025 |
Dearborn University Center
Building # 1001060 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021541 | Dearborn University Center Renick University Center First Floor Renovations | Substantial Completion | 04/01/2024 | 12/20/2024 |
Dow Herbert H Building
Building # 1000447 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020541 | Room 1043D 1043E & 1206 Renovations | Substantial Completion | 05/08/2023 | 08/11/2023 |
P00021109 | Elevator #9 Replacement | Construction | 09/16/2024 | 12/17/2024 |
P00021412 | Dow Manufacturing Lab Renovation | Construction | 09/13/2024 | 07/18/2025 |
Duderstadt James and Anne Center
Building # 1000396 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022280 | Create New Office 1384A | Substantial Completion | 06/10/2024 | 08/13/2024 |
East Ann Arbor Ambulatory Surgical Center
Building # 1005038 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020356 | U-M Health East Ann Arbor Ambulatory Surgical Center CSPD Temporary Mobile Unit & Infrastructure | Construction | 09/04/2023 | 03/08/2024 |
East Ann Arbor Health and Geriatrics Center
Building # 1000350 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021657 | U-M Health EAA Health and Geriatrics Center MRI Replacement | Construction | 10/28/2024 | 05/28/2025 |
P00022216 | FY24 EAA BI Room 1737 | Construction | 01/10/2025 | 04/15/2025 |
East Hall
Building # 1000166 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020559 | Room 4M64 | Substantial Completion | 05/06/2024 | 07/12/2024 |
P00020821 | Refurbish-Replace Strobic Exhaust Fans | Construction Documents | 07/14/2025 | 11/07/2025 |
P00021220 | Fire Alarm Upgrade | Construction | 12/02/2024 | 12/31/2025 |
P00021345 | Rooms 1056 & 1069 Renovations | Substantial Completion | 06/12/2023 | 11/30/2023 |
P00022708 | Renovate Labs 4250 and 4252 | Construction Documents | 02/03/2025 | 09/12/2025 |
P00022711 | Renovate Lab 4245 and Adjacent Rooms | Construction Documents | 02/03/2025 | 08/15/2025 |
P00022740 | Renovate First Floor Rooms | Construction Documents | 03/03/2025 | 05/30/2025 |
East Quadrangle
Building # 1000054 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022068 | Photography Room B601 Renovation | Substantial Completion | 05/31/2024 | 08/23/2024 |
Electrical Engineering And Computer Science Bld
Building # 1000448 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019748 | High Purity Water System Repairs | Construction Documents | 01/06/2025 | 08/29/2025 |
P00021707 | Renovate Lab1327 | Construction | 12/06/2024 | 03/28/2025 |
P00023046 | Rooms 3308 and 3400 Conference Room Renovations | Construction Documents | 05/05/2025 | 07/25/2025 |
P00023107 | Room 3214 Renovation | Construction Documents | 11/19/2024 | 02/10/2025 |
Engineering Research Building 1
Building # 1000435 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021517 | Rooms 113 & 113A Renovations | Construction Documents | 03/11/2024 | 08/30/2024 |
Engineering Research Support Bld
Building # 1002505 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020563 | Vacuum Chamber | Construction | 04/24/2023 | 02/03/2025 |
Facilities Services Building A
Building # 1000800 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022254 | Maintenance Services Offices Furniture | Construction Documents |
Facilities Services Building B
Building # 1000801 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020370 | FSB Truss Shoring Phase 3 | Bid-Award | 11/21/2022 | 02/24/2023 |
Fire Serv Instr Res Center
Building # 1000409 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022729 | Boiler Replacement | Construction Documents | 06/03/2025 | 09/19/2025 |
Fletcher St Parking Structure
Building # 1000254 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021713 | Fletcher Street Parking Structure Repairs and Upgrades | Construction | 05/06/2024 | 08/15/2025 |
Francis Thomas Jr Public Health
Building # 1000234 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022549 | 10 Ton Chiller Replacement | Construction Documents | 01/13/2025 | 04/04/2025 |
Frankel Samuel And Jean Cardiovascular Center
Building # 1005109 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019786 | U-M Health Frankel Cardiovascular Center Level One Renovations | Construction | 01/16/2023 | 12/13/2024 |
P00021656 | U-M Health Frankel Samuel and Jean Cardiovascular Center FY24 EP lab #4 Replacement | Construction | 11/12/2024 | 02/28/2025 |
P00021679 | FY24 CVC DDC Controls (Yr1) | Schematic Design | 05/12/2025 | 03/13/2026 |
Gerstacker Carl A Building
Building # 1000437 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021788 | Heating Hot Water Boiler Replacement | Substantial Completion | 08/05/2024 | 12/03/2024 |
P00022157 | Air Compressor Replacement | Construction | 12/23/2024 | 03/14/2025 |
Ginsberg Edward and Rosalie Building
Building # 1005507 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00017959 | Edward and Rosalie Ginsberg Building | Construction | 04/18/2023 | 02/13/2025 |
Glen Ave Parking Structure
Building # 1000331 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022444 | Fall Prevention Fencing | Schematic Design | 04/01/2025 | 08/08/2025 |
Hadley Family Recreation and Well-Being Center
Building # 1005445 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00007755 | Hadley Family Recreation & Well-Being Center | Construction | 12/14/2022 | 07/31/2025 |
Hatcher H North Graduate Library
Building # 1000185 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019685 | Rehabilitate North and West Entrances and Exterior Repairs | Substantial Completion | 06/30/2023 | 12/06/2024 |
P00022159 | Replace Perimeter Heat and AC Units | Construction Documents | 05/12/2025 | 09/12/2025 |
P00022572 | Replace East Accessible Ramp and Masonry Repairs | Construction Documents | 05/12/2025 | 08/22/2025 |
Hatcher Harlan H South Graduate Library
Building # 1000181 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019823 | Modifications to Stairwell Doors | Construction | 02/24/2023 | 09/27/2024 |
P00020606 | Fan Coil and Humidifier Replacement | Construction Documents | 06/16/2025 | 10/31/2025 |
P00021373 | Hatcher South Graduate Library Windows and Entrance Door Replacement | Construction | 05/12/2025 | 08/22/2025 |
Health Service
Building # 1000176 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021142 | Refeed Fire Pump from Substation | Construction | 01/06/2025 | 02/14/2025 |
Hill St Parking Structure
Building # 1000253 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022522 | Fall Prevention Fencing | Schematic Design | 03/03/2025 | 08/08/2025 |
P00022780 | 2025 Concrete & Waterproofing Repairs | Construction Documents | 05/05/2025 | 10/31/2025 |
Hutchins Hall
Building # 1000179 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019898 | Cafe Gate Renovation | Construction | 07/31/2023 | 08/17/2023 |
P00020751 | Replace Steam Coils | Construction Documents | 02/24/2025 | 05/30/2025 |
Industrial And Operations Engineering Building
Building # 1000429 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019652 | Restroom G870M Renovation | Construction | 01/16/2023 | 03/17/2023 |
P00020260 | Industrial and Operations Engineering Building First Floor and Ground Floor Renovation | Substantial Completion | 05/08/2024 | 12/06/2024 |
P00022024 | MCC and Secondary Electrical Distribution System Replacement | Construction | 05/05/2025 | 09/19/2025 |
Jeffries Hall
Building # 1005235 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021575 | Classroom Occupancy Sensors | Construction | 06/03/2024 | 01/03/2025 |
Kahn D Dan and Betty Health Care Pavilion
Building # 1005440 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00011094 | U-M Health D. Dan and Betty Kahn Health Care Pavilion | Construction | 03/01/2021 | 06/01/2025 |
P00022733 | Exterior Wayfinding Signage Updates | Construction Documents | 07/07/2025 | 09/01/2025 |
Kellogg W K Eye Center
Building # 1000324 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019473 | Kellogg W K Eye Center and Brehm Tower Boiler and Hot Water Feed Interconnection | Construction | 07/13/2023 | 01/28/2025 |
P00019579 | Refurbish AHU-1 and AHU-2 | Bid-Award | 10/20/2025 | 05/08/2026 |
P00022163 | Room 606 & 610 Lab and Office Renovation | Construction Documents | 10/07/2024 | 01/03/2025 |
Kellogg W K Foundation Institute
Building # 1000162 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021514 | ECM - Dental AH-6 & 7 Controls Upgrade | Construction Documents | 04/29/2024 | 08/02/2024 |
P00021654 | Digital Dentistry Lab in Rooms G310 and G311A | Construction | 07/01/2024 | 12/31/2024 |
P00022094 | Phoenix Lab Valves | Construction Documents | 03/24/2025 | 06/27/2025 |
P00022113 | Room 2519 Computer Workroom | Construction | 11/01/2024 | 02/28/2025 |
P00022397 | Museum Modifications | Construction | 09/23/2024 | 12/12/2024 |
P00022953 | Renovate Auditoriums G322 - G378 - G390 | Schematic Design | ||
P00023002 | Replace Sanitary Pipe Phase 1 | Construction Documents | 04/21/2025 | 07/11/2025 |
Lane Hall
Building # 1000183 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022339 | Power Door Operators 1136 and G112 | Construction | 02/26/2024 | 06/07/2024 |
Leinweber Computer Science and Information Bldg
Building # 1005504 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00014414 | Leinweber Computer Science and Information Building | Substantial Completion | 05/23/2022 | 12/06/2024 |
Lorch Hall
Building # 1000154 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00018453 | HVAC Replacement | Construction | 02/03/2022 | 06/29/2023 |
P00022689 | Identified Occupant Modifications | Construction Documents | 12/06/2024 | 01/16/2025 |
Mary Sue Coleman Hall
Building # 1005036 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019583 | Renovate Room 3358 for Lab Space | Bid-Award | 01/27/2025 | 08/08/2025 |
Mason Hall
Building # 1000197 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021965 | Room 2432 Gender Inclusive Restroom | Construction |
Med Ctr N Entrance Parking Structure
Building # 1000300 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021614 | Elevator Replacements | Construction | 12/02/2024 | 08/11/2025 |
Medical Center Dr Parking Struct
Building # 1000315 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022783 | P2 Concrete & Waterproofing Repairs 2025 | Construction Documents | 05/05/2025 | 10/30/2026 |
Medical Science Unit I
Building # 1000190 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00016195 | Medical Science Unit I B and D Wings Renovation | Construction | 05/01/2023 | 05/05/2025 |
P00019968 | Office Suite Renovation 5311 | Construction | 05/30/2022 | 10/18/2024 |
P00020009 | ECM - Med Sci I - HVAC Controls Upgrades | Construction | 01/29/2024 | 05/20/2025 |
P00020884 | Remodel Office Suite 7330 | Substantial Completion | 03/30/2023 | 09/27/2024 |
P00021405 | Installation of Acoustical Booths | Construction | 02/12/2024 | 12/27/2024 |
P00021743 | Room 5442 Office Suite | Construction | 04/29/2024 | 09/13/2024 |
P00022147 | Room 2304 Shop Space | Construction Documents | ||
P00022916 | Room 5312D Renovate for Laser Lab | Schematic Design |
Medical Science Unit II
Building # 1000200 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00018192 | Anatomical Donations - Rooms 3618B & 3618C | Construction Documents | 02/24/2025 | 07/11/2025 |
P00019251 | Renovate 2655 & 2659 | Schematic Design | 03/24/2025 | 06/20/2025 |
P00020818 | Replace Eight Motor Control Centers | Construction | 05/06/2024 | 10/11/2024 |
P00021741 | Renovate 5609 5635 and Suite 5641 for Offices | Construction | ||
P00021742 | Suite 3726 & 3722 Lab and Office Renovation | Construction Documents | 04/15/2024 | 02/12/2025 |
P00022170 | Room 5713A Tissue Culture Room | Construction Documents | 09/02/2024 | 11/29/2024 |
P00022172 | Rooms 2710 & 2736 Classroom Renovations | Construction | 08/05/2024 | 02/10/2025 |
P00022564 | Renovate 7th Floor Lab Spaces | Construction Documents | 05/06/2024 | 08/16/2024 |
P00022932 | Room 6748 & 6748A Furniture | Construction Documents | 10/21/2024 | 12/20/2024 |
P00022989 | Elevators #5 & #6 Replacements | Construction Documents | 07/06/2026 | 01/06/2027 |
P00023089 | ULAM Operations Renovations | Schematic Design | 01/02/2026 | 07/02/2026 |
Medical Sciences Research Bldg I
Building # 1000223 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019578 | Refurbish AHU-1 | Construction | 11/04/2024 | 03/14/2025 |
P00019582 | Upgrade AHU-2 and AHU-3 Fans and VSDs | Substantial Completion | 11/22/2023 | 09/06/2024 |
P00022175 | 2nd Floor Lighting and Water Systems | Construction Documents |
Medical Sciences Research Bldg II
Building # 1000213 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021055 | B-Level Renovation | Construction Documents | ||
P00021521 | Suite 1570 and 1560 Finishes, Furniture and Lighting upgrade | Construction | 12/06/2024 | 02/28/2025 |
P00022166 | 2560 Suite Furniture and Finish Upgrade | Substantial Completion | 10/01/2024 | 10/31/2024 |
P00022375 | Room 2580 Lab Renovation | Construction | 11/15/2024 | 04/15/2025 |
P00022376 | Room 3577 Lab Renovation | Construction | 11/01/2024 | 03/31/2025 |
P00022381 | Suite 1596 Dividing Wall and Office Furniture | Construction | 11/22/2024 | 04/18/2025 |
P00022790 | ECM - Chiller Room HVAC Controls Upgrade | Construction | 01/13/2025 | 05/30/2025 |
Medical Sciences Research Bldg III
Building # 1000229 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019897 | Phoenix Lab Controls System Upgrade | Construction | 10/30/2023 | 01/17/2025 |
P00021916 | Room 2404 Tunnel Washer Sanitary Pipe Repair | Construction | 10/03/2024 | 01/08/2025 |
P00023189 | Elevators #15 & #16 Replacements | Schematic Design | 02/02/2026 | 08/05/2026 |
Michigan League
Building # 1000191 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021848 | ECM - Kitchen DX Compressor | Construction | 09/23/2024 | 11/29/2024 |
Michigan Memorial Phoenix Project Laboratory
Building # 1000404 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00015722 | Refurbish Sidewalk Lift and Adjacent Concrete | Construction Documents | 05/06/2025 | 08/22/2025 |
P00020704 | Renovate Lab 1066 | Construction | 08/14/2023 | 03/26/2024 |
Michigan Stadium
Building # 1000711 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022102 | Limited Bowl & Parapet Re-Coating | Construction | 04/07/2025 | 08/01/2025 |
Moore Earl V Bldg
Building # 1000440 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020459 | Room 1306 and 1315A Multiperson Offices | Construction Documents | 02/27/2023 | 05/18/2023 |
P00022894 | Room 1315A Office Cubicle | Construction Documents |
Mott Childrens Von Voigtlander Womens Hospitals
Building # 1005173 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020347 | CW OR Corridor Pressurization | Construction | 06/24/2024 | 01/14/2025 |
P00021671 | U-M Health Mott Childrens New Children's Emergency Services Fast Track Clinic | Construction | 08/30/2024 | 03/28/2025 |
P00021710 | FY24 CES Perimeter Access Control | Construction | 03/17/2025 | 05/19/2025 |
P00021732 | FY24 CES Three Ligature Free Exam Rooms | Construction | 05/06/2025 | 08/04/2025 |
P00021926 | FY24 CW 3rd Floor Pre-Op & Recovery | Construction | 11/18/2024 | 04/25/2025 |
P00022846 | FY25 Mott CSPD Upgrades | Schematic Design | 09/01/2025 | 12/12/2025 |
Multiple Blocks
Building # 0000001 - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00015418 | Nichols Drive Slope Stabilization | Construction | 01/06/2025 | 09/30/2025 |
P00016251 | Diag Improvements | Construction Documents | 05/05/2025 | 08/15/2025 |
P00020720 | Radrick Farms Golf Course Erosion Repairs | Construction | 12/02/2024 | 12/31/2026 |
P00022075 | Diag Drainage Improvements | Schematic Design | ||
P00022181 | Wooden Stair Removal - Glen Ave to West Medical Center Dr | Construction | 06/21/2024 | 10/25/2024 |
P00022594 | 2025 Sidewalk Program | Design Development | 06/01/2025 | 10/31/2025 |
P00022936 | Multiple Exterior Lighting Improvements For CoE On North Campus | Construction Documents | 01/06/2025 | 02/21/2025 |
P00022996 | 2025 Asphalt Maintenance Program | Schematic Design | 06/16/2025 | 10/31/2025 |
P00023001 | Hubbard Road Water Main Replacement | Schematic Design | 05/12/2025 | 08/29/2025 |
P00023129 | FY25 Bridge Repairs | Schematic Design | 05/12/2025 | 08/15/2025 |
P00023254 | City of Ann Arbor - State Street (South University to William) | Construction Documents | 05/05/2025 | 05/29/2026 |
Multiple Buildings
Building # 1080002 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00017506 | UMHS FCC to CSSB Central Dispatch Network Upgrades | Bid-Award | 12/16/2024 | 08/29/2025 |
P00017627 | Verizon 5G Antennas Construction and Inspections | Construction | 09/02/2019 | 05/27/2022 |
P00017961 | Cold Room Improvements | Construction Documents | 04/28/2025 | 07/18/2025 |
P00018822 | Backflow Prevention Phase 7 | Construction Documents | 12/16/2024 | 06/27/2025 |
P00019390 | Arbor Lakes 1-3 Card Reader Replacement Consultation | Substantial Completion | 04/04/2022 | 09/30/2022 |
P00019651 | Power Assisted Door Operators - EECS and Beyster Building | Substantial Completion | 10/16/2023 | 06/28/2024 |
P00019731 | Upgrade Existing General Fund Refrigerant Monitor Systems | Construction | 02/07/2022 | 12/27/2024 |
P00019754 | Signage for Medical School Buildings | Construction Documents | 10/27/2025 | 02/27/2026 |
P00020142 | Medical School Facilities - Door Hardware Modifications | Schematic Design | 11/25/2024 | 03/31/2025 |
P00020174 | Automatic Door Operators on Exterior Entrances and Vestibules | Construction | 12/20/2023 | 01/23/2026 |
P00020239 | Multiple Buildings Electric Vehicle Charging Stations | Construction | 09/12/2022 | 03/31/2026 |
P00020451 | ADA Power Door Operators | Construction Documents | 02/06/2023 | 11/30/2023 |
P00020722 | Chiller Overhauls & Cooling Tower Restoration | Construction | 04/03/2023 | 12/27/2024 |
P00020747 | FY23 Exterior Door Improvements | Construction Documents | 05/05/2025 | 08/22/2025 |
P00020822 | Fire Pump MOSCAD Monitoring Points | Construction | 01/03/2023 | 11/29/2024 |
P00020965 | Multiple Buildings PARCS Replacement and Permit Management with LPR | Bid-Award | 03/10/2025 | 07/17/2026 |
P00020999 | Upgrade Existing General Fund Refrigerant Monitor Systems | Construction | 04/03/2023 | 12/27/2024 |
P00021371 | U-M Health C&W and UH FY24 Infant Security System Replacement (HUGs) | Bid-Award | 01/16/2025 | 09/21/2026 |
P00021605 | Automated Bedding System | Bid-Award | 02/28/2025 | 09/30/2025 |
P00021634 | Classroom Lockset Interconnected | Construction | 03/25/2024 | 09/04/2026 |
P00021663 | U-M Health Multiple Buildings FY24 Pharmacy UPS 795 Upgrades | Construction | 12/02/2024 | 08/29/2025 |
P00021665 | U-M Health Multiple Buildings FY24 AES-PES Expansion | Construction | 01/06/2025 | 02/20/2026 |
P00021695 | U-M Health Multiple Buildings FY24 EAA Infrastructure Yr5 | Construction | 11/21/2024 | 08/25/2025 |
P00021722 | FY24 UH PTube Safety Upgrades | Construction | 01/06/2025 | 03/31/2025 |
P00021727 | Cooling Tower and MRL Elevator Access Improvements | Construction Documents | 09/29/2025 | 01/02/2026 |
P00021894 | FY24 Variable Frequency Drive (VFD) Replacement | Construction Documents | 04/01/2024 | 12/20/2024 |
P00021951 | Data Line Relocation | Construction Documents | 03/04/2024 | 09/06/2024 |
P00022046 | Minor ADA Modifications FY 24 and FY 25 Without Drawings | Construction Documents | 05/26/2025 | 03/27/2026 |
P00022055 | Eyewash Station Phase 4 | Construction | 06/10/2024 | 08/29/2025 |
P00022062 | MSRB - Heating Hot Water Interconnect | Construction Documents | 06/27/2025 | 12/05/2025 |
P00022086 | Hoist Crane Assessment | Construction Documents | 01/06/2025 | |
P00022104 | Upgrade Existing General Fund Refrigerant Monitor Systems | Construction | 04/01/2024 | 12/27/2024 |
P00022105 | Chiller Overhauls & Cooling Tower Restoration | Construction | 04/01/2024 | 12/27/2024 |
P00022202 | Permanent Power at Ingalls Mall for Outdoor Events | Construction Documents | 05/05/2025 | 08/29/2025 |
P00022414 | Crisler Center - Revised Underground Steam and Condensate | Schematic Design | 09/08/2025 | 02/20/2026 |
P00022595 | Non Accessible Entry Signage | Construction Documents | 03/04/2025 | 08/18/2025 |
P00022716 | Lactation and Privacy Pods | Construction Documents | 01/23/2025 | 02/13/2025 |
P00022789 | NCRC Building Entrances Revolving Door Replacement | Schematic Design | ||
P00022810 | Facilities Maintenance Projects FY25 | Construction Documents | 10/31/2024 | 06/30/2025 |
P00022831 | FY 25 Briarwood Facades Yr2 | Substantial Completion | 09/03/2024 | 11/29/2024 |
P00023021 | FY25 Variable Frequency Drive (VFD) Replacement | Construction Documents | 05/26/2025 | 02/06/2026 |
P00023258 | Upgrade Existing General Fund Refrigerant Monitor Systems | Construction | 03/31/2025 | 12/19/2025 |
P00023259 | Chiller Overhauls & Cooling Tower Restoration | Construction | 03/31/2025 | 12/30/2025 |
Multiple Tunnel Sections
Building # 3010030 - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019365 | Condensate System Replacement POR 405-416 and 712-910 | Construction | 05/20/2024 | 11/29/2024 |
Naval Architecture and Marine Engineering
Building # 1000415 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00023218 | Roof Replacement | Construction Documents | 06/02/2025 | 08/22/2025 |
Neal Homer A Laboratory
Building # 1005517 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022639 | Lab 3215 & 3223 Renovation | Schematic Design | 05/12/2025 | 08/29/2025 |
P00022653 | Renovate Lab 3231 | Schematic Design | 05/12/2025 | 08/29/2025 |
P00022654 | Renovate Lab Suite 3214 | Schematic Design | 06/02/2025 | 09/19/2025 |
P00023246 | Fire Rated Barrier Addition | Construction Documents | 06/30/2025 | 09/19/2025 |
New Facility
Building # 1009990 - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019359 | Flint College of Innovation & Technology Building | Construction | 03/26/2024 | 02/16/2026 |
P00021068 | U-M Center for Innovation | Construction | 12/18/2023 | 06/14/2027 |
P00022879 | Ross Executive MBA Los Angeles Leasehold Improvements | Design Development | 04/09/2025 | 11/30/2025 |
New Pharmacy Building
Building # 1005492 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00009923 | New Building for the College of Pharmacy | Construction | 02/01/2023 | 06/20/2025 |
Newberry Hall
Building # 1000178 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020804 | Humidifier Replacement | Construction | 05/01/2023 | 06/14/2024 |
P00020828 | East Entrance Security Desk Reconfiguration | Construction Documents | 05/13/2024 | 07/26/2024 |
North Campus Administrative Complex
Building # 1000399 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021256 | Repair NCAC Vehicle Bridge and Entry Plaza | Construction | 08/01/2024 | 06/30/2025 |
North Campus Auxiliary Support Building
Building # 1005223 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020931 | FY 23 NCASB Infrastructure - Phase 1 | Construction | 10/09/2024 | 12/06/2024 |
North Campus Research Complex Building 10
Building # 1005253 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022712 | Auditorium Updates and Modifications | Construction | 09/09/2024 | 01/24/2025 |
North Campus Research Complex Building 16
Building # 1005256 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00018761 | Replace Generator PLC | Construction | 07/18/2022 | 02/16/2024 |
North Campus Research Complex Building 22
Building # 1005260 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022334 | Office Renovation in Suite 1016 | Construction | 11/01/2024 | 03/31/2025 |
North Campus Research Complex Building 25
Building # 1005262 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020186 | Renovation of G-Level Vivarium | Substantial Completion | 02/15/2023 | 04/22/2024 |
P00020633 | Lab Renovation in Suite G49 | Substantial Completion | 04/01/2024 | 10/11/2024 |
P00021516 | Renovation of Rooms G39 and G40 | Construction Documents | 07/01/2025 | 12/31/2025 |
North Campus Research Complex Building 35
Building # 1005266 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022792 | Molecular Lab Fume Hood | Construction Documents | 10/07/2024 | 12/06/2024 |
North Campus Research Complex Building 520
Building # 1005281 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021091 | Rooms G141 & G142 Observation Lab | Substantial Completion | 08/10/2023 | 03/01/2024 |
North Campus Research Complex Building 60
Building # 1005270 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022382 | Room 1645 Brain Bank | Substantial Completion | 07/01/2024 | 12/01/2024 |
North Campus Research Complex Building 80
Building # 1005273 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00023041 | Room 130 Gender Inclusive Restroom and Room 132 Kitchenette | Schematic Design |
North Quadrangle Residential and Academic Complex
Building # 1005177 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021988 | Room 7351 Demountable Wall | Construction |
Northville Health Center
Building # 1005341 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021991 | FY25 NHC Renovation for New Services | Substantial Completion | 09/09/2024 | 12/20/2024 |
P00022035 | FY25 NHC CSPD Upgrade | Construction | 09/07/2024 | 12/19/2024 |
Northwood Community Center
Building # 1000600 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021572 | Bridge Repair | Construction | 05/01/2024 | 04/30/2025 |
Northwood IV Apts 641
Building # 1000641 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022811 | Foundation Wall Replacement at Units 1837-1843 | Construction Documents | 03/24/2025 | 07/04/2025 |
Observatory Hall
Building # 1000851 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00015356 | Observatory Hall Reserve Officers Training Corps Space Renovation | Construction | 04/09/2024 | 05/13/2025 |
Palmer Drive Parking Structure
Building # 1000263 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022016 | Fire Suppression System Repairs | Construction Documents | 01/27/2025 | 06/19/2025 |
P00022988 | Structural Condition Assessment and Repairs | Schematic Design | 05/12/2025 | 08/15/2025 |
Perry Building
Building # 1000890 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00023097 | Surface Drainage Improvements | Construction Documents | 05/26/2025 | 06/27/2025 |
Power Center For Performing Arts
Building # 1000180 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020854 | Heating Pumps Replacement | Construction Documents | 03/03/2025 | 04/18/2025 |
Rackham Horace H School Of Graduate Studies
Building # 1000172 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019738 | Reflection Wellness 2102 | Construction Documents | 01/07/2025 | 06/02/2025 |
P00020723 | Replace Heating Hot Water Piping | Construction | 10/30/2023 | 11/01/2024 |
Randall Harrison M Laboratory
Building # 1000208 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021409 | Renovate Sub Basement Labs | Bid-Award | 07/01/2024 | 02/14/2025 |
P00023283 | Replace Secondary Electrical Distribution | Schematic Design | 09/01/2025 | 02/13/2026 |
Research Museums Center
Building # 1000812 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019789 | Redundant Compressor for Cold Room 1510 | Bid-Award | 12/02/2024 | 07/18/2025 |
P00020086 | Renovate Molecular Lab Room 1080 | Construction Documents | 07/03/2023 | 06/07/2024 |
P00022124 | Humidification Boiler Replacement | Construction Documents | 09/08/2025 | 01/01/2026 |
P00022557 | Generator Load Study | Schematic Design |
Rogel Cancer Center
Building # 1000301 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00017472 | Rogel Cancer Center FY20 CC Infrastructure Replacement 2 | Construction | 10/10/2022 | 12/31/2024 |
P00020904 | U-M Health Rogel Cancer Center Infrastructure Upgrades | Bid-Award | 01/09/2025 | 03/13/2026 |
P00022338 | Power Door Operators Elevator Lobby levels 3 to 7 | Substantial Completion | 03/11/2024 | 04/26/2024 |
P00022962 | Levels 3-7 Kitchenette Renovations and Furniture | Construction Documents |
Ross School of Business Building
Building # 1005188 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021793 | Office Suite 2400 Modifications | Construction Documents | 10/28/2024 | 01/03/2025 |
P00022036 | Wall Paneling Repairs | Schematic Design |
School of Kinesiology Building
Building # 1000211 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021694 | Renovation of Room 3300 | Construction | 07/04/2024 | 12/12/2024 |
P00022565 | Add Two-Way Communication Devices at Elevators | Substantial Completion | 03/24/2025 | 05/06/2025 |
School of Nursing Building 1
Building # 1000333 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020425 | Elevator #8 Replacement | Construction Documents | 09/01/2025 | 12/19/2025 |
P00020986 | School of Nursing Building 1 Classroom and Interior Renovation | Construction | 04/29/2024 | 01/20/2025 |
P00022043 | Renovate First Floor West | Construction Documents | 07/07/2025 | 11/14/2025 |
School of Social Work Building
Building # 1000219 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022013 | School of Social Work Courtyard Improvements | Bid-Award | 03/03/2025 | 08/15/2025 |
P00022530 | Room Signage Replacement | Construction | 11/11/2024 | 01/10/2025 |
Shapiro Harold T and Vivian B Library
Building # 1000227 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020853 | Sanitary Pump Replacement | Construction Documents | 02/24/2025 | 03/28/2025 |
P00022889 | New PA System | Construction Documents | 05/05/2025 | 09/12/2025 |
South Quadrangle
Building # 1000063 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021910 | Afro American Lounge Renovation | Substantial Completion | 04/01/2024 | 09/27/2024 |
Stamps Auditorium
Building # 1005224 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020041 | Stamps Auditorium Renovate House Lighting and Controls | Construction | 03/13/2023 | 08/18/2023 |
Stearns Frederick Building
Building # 1000445 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00023289 | Fire Alarm Upgrade | Construction Documents | 05/26/2025 | 08/01/2025 |
Tappan Hall
Building # 1000216 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020167 | Rooms 10B 10C 20 20B and 20C Renovation | Substantial Completion | 01/19/2023 | 12/16/2024 |
Taubman A Alfred Biomedical Science Research Bldg
Building # 1005037 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00016153 | Door Hardware Modifications and Protection | Construction Documents | 02/01/2023 | 09/30/2024 |
P00017347 | Install VSDs on Primary CHW Pumps and Controls Modifications | Construction | 12/28/2020 | 12/20/2024 |
P00019525 | Room D400 Sterilizer Installation | Construction Documents | 10/10/2022 | 02/17/2023 |
P00021719 | Room 2120 Lab Renovation | Substantial Completion | 05/20/2024 | 08/02/2024 |
P00022209 | Kahn Auditorium ADA Modifications | Construction | 08/23/2024 | 08/15/2025 |
P00022281 | Exterior Soffit Air Barrier Repairs | Bid-Award | 05/05/2025 | 08/08/2025 |
P00022361 | Energy Recovery System Optimization | Construction Documents | 04/28/2025 | 07/04/2025 |
Taubman A Alfred Health Care Ctr
Building # 1000317 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00020487 | U-M Health Taubman HealthCenter Fire Alarm Replacement | Construction | 06/24/2024 | 08/12/2025 |
P00021878 | U-M Health Taubman A Alfred Health Care Ctr Air Handling Unit Replacement | Construction | 09/10/2024 | 03/06/2026 |
P00021886 | FY24 General Rad Room Replacement THC 2302 | Construction | 08/19/2024 | 12/16/2024 |
P00021890 | FY24 Replace THC Flouro Room 2504 | Construction | 02/03/2025 | 06/06/2025 |
Taubman A Alfred Health Sciences Library
Building # 1000209 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022179 | Room 6215 Furniture | Construction | 07/22/2024 | 07/26/2024 |
Thayer St Parking Structure
Building # 1000259 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022784 | Facade Investigation & Repairs | Schematic Design | 05/05/2025 | 08/15/2025 |
Undergraduate Science Building
Building # 1005046 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022084 | 2nd and 4th Floor Student Engagement Spaces | Substantial Completion | 05/06/2024 | 07/31/2024 |
P00022106 | Replace Domestic Cold and Hot Water Pipe and Booster Pump | Construction | 04/14/2025 | 07/25/2025 |
University Hospital
Building # 1000316 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00013052 | U-M Health University Hospital Electrical Substation Replacement | Construction | 10/21/2022 | 04/30/2025 |
P00020346 | UH OR Corridor Pressurization | Construction | 07/29/2024 | 02/19/2025 |
P00020361 | UH ATS Replacements | Construction | 07/09/2024 | 12/10/2024 |
P00020528 | UH Kitchen Cook - Chill Renovation | Construction | 11/19/2024 | 08/29/2025 |
P00020702 | University Hospital DDC Controls | Bid-Award | 03/10/2025 | 03/31/2028 |
P00021641 | FY24 UH Medical Air Compressor | Bid-Award | 06/16/2025 | 07/15/2025 |
P00021678 | U-M Health University Hospital FY24 UH DDC Controls Upgrade (Yr2) | Bid-Award | 03/10/2025 | 03/31/2028 |
P00022119 | U-M Health University Hospital FY24 IR#1 Replacement | Bid-Award | 02/24/2025 | 08/27/2025 |
P00022123 | UH CSPD Emergent Upgrades | Construction | 03/06/2024 | 01/17/2025 |
P00022205 | U-M Health University Hospital FY24 CT#4 Replacement | Bid-Award | 02/10/2025 | 08/27/2025 |
P00022369 | Liquid Nitrogen Tank Upgrade | Bid-Award | 01/13/2025 | 06/16/2025 |
P00022862 | UH Radiation Oncology TX6 Removal | Construction Documents | 04/11/2025 | 09/26/2025 |
University Hospital South Unit 1
Building # 1000309 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021925 | UH South Unit 1 Water Service | Construction Documents | 04/14/2025 | 05/29/2025 |
University Hospital South Unit 2
Building # 1000312 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022577 | U-M Health University Hospital South Renovation | Construction | 09/02/2024 | 03/31/2025 |
Vaughan Henry Frieze Public Health Building
Building # 1000204 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021309 | Renovate Lab 7606 A & B | Construction Documents | 03/11/2024 | 02/05/2025 |
P00021923 | Room 7642 Lab Modifications | Substantial Completion | 04/30/2024 | 11/04/2024 |
Walgreen Charles R Jr Drama Center
Building # 1005059 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022744 | Heating Hot Water Boilers Replacement | Construction Documents | 04/14/2025 | 07/25/2025 |
Wall Street East Parking Structure
Building # 1005193 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022781 | 2025 Concrete & Waterproofing Repairs | Construction Documents | 05/05/2025 | 09/30/2025 |
Weill Joan & Sanford Hall
Building # 1005101 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00021392 | Southwest Stair and Plaza Replacement | Construction Documents | 06/02/2025 | 08/22/2025 |
Weiser Hall
Building # 1000165 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00018150 | Renovate 6th Floor Office Areas | Construction Documents | 03/31/2025 | 08/15/2025 |
P00020695 | Weiser Hall Lowrise Circulation Renovation | Construction | 05/05/2025 | 08/08/2025 |
West Hall
Building # 1000167 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019788 | ADA PADO Installations | Substantial Completion | 04/03/2022 | 05/26/2023 |
P00020562 | West Hall Laboratory Rm 130 | Construction | 04/24/2023 | 04/26/2024 |
P00021047 | Wave Generator System | Construction Documents | 05/25/2025 | 10/03/2025 |
Wyly Sam Hall
Building # 1000135 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00019910 | Entry Lobby Heating - Construction | Construction | 01/04/2021 | 10/13/2023 |
Zina Pitcher Parking Structure
Building # 1005580 - View Map - View Regent Action Items
Project Number | Project | Phase | Est Const Start Date | Est Const End Date |
---|---|---|---|---|
P00022426 | U-M Health Zina Pitcher Parking Structure | Construction | 11/18/2024 | 12/15/2025 |