Data

202 South Thayer Building

Project Number: P100517905001

Budget: $18 million

Schedule:

  • Estimated Construction Start: May 2005
  • Estimated Construction Completion: Summer 2006

Square Ft.: 60,000 gross sq. ft.

 

Project Team

Design Team: Diamond Schmitt Architects

Construction Team: Walbridge Aldinger Company

Owner Team:

  • Project Lead: Architecture, Engineering and Construction
  • Support Units:
    • College of Literature, Science, and the Arts
    • Occupational Safety and Environmental Health
    • Plant Operations