Project Data

Biomedical Engineering Project – Ann and Robert H Lurie Biomedical Engineering Building Laboratory Addition and Renovation

Project Number: P100040602001

Budget: $20 million

Schedule:

  • Addition:
    • Estimated Construction Start: January 2004
    • Estimated Construction Completion: June 2005 
  • Renovation:
    • Estimated Construction Start: January 2006
    • Estimated Construction Completion: September 2006

Square Ft.: 62,000 gross sq. ft. addition and renovation

 

Project Team

Design Team: Zimmer Gunsul Frasca Partnership

Construction Team: Skanska USA Building Inc.

Owner Team: