Project Details

Camp Davis Rocky Mountain Field Station Student Cabin and Support Facilities Replacement

Project Number: P00011089

Budget: $6.5 million

Schedule:

  • Construction Start: Summer 2018
  • Construction Completed: June 2019

Square Feet:

  •  Addition – 10,800 gross square feet

Design Team: Krikor Architecture

Construction Team: Century Contractors Inc.

 

Maps and Construction Logistics

N/A

Design

N/A

News

Thirty new modular cabins to be built at Camp Davis – February 15, 2018