Central Campus Classroom Building and the Alexander G. Ruthven Building Renovation

Project Number: P00012150

Budget: $150 million

Schedule:

  • Construction Start: Fall 2018
  • Construction Completed: December 2021

Square Feet:

  • Addition – 100,000 gross square feet
  • Renovation – 135,000 gross square feet

Design Team: Harley Ellis Devereaux and Stecker Labau Arneill McManus Collaborative

Construction Team: Barton Malow

 

Maps and Construction Logistics

Area Map

Central Campus Map

Design

Classroom Building and Ruthven Renovation

Classroom Building Main Level

Classroom Building Level 2

Classroom Building and Ruthven Renovation Context Map

News

Innovative Classroom Building Opening to Active, Team-Based Learning
December 16, 2021

New Central Campus Building to Provide Innovative Classrooms
December 6, 2018

Historic Ruthven Building to Receive $150M Renovation and Addition
December 8, 2016