Project Data

Charles R. Walgreen, Jr. Drama Center and Stamps Auditorium

Project Number: P100505903001

Budget: $42.8 million

Schedule:

  • Estimated Construction Start: May 2005 
  • Estimated Construction Completion: Summer 2007 

Square Ft.: 97,500 gross sq. ft.

 

Project Team

Design Team: Kuwabara Payne McKenna and Blumberg Architects

Construction Team: Skanska USA

Owner Team:

 