Project Number: P00004526
Budget: $7 million
Schedule:
- Estimated Construction Start: Summer 2012
- Estimated Construction Completion: Fall 2013
Project Team
Design Team: URS Corporation
Construction Team: John E. Green
Owner Team:
- Project Lead: Architecture, Engineering and Construction
- Support Units: