Project Number: P100509202001
Budget: $40 million
Schedule:
- Estimated Construction Start: Fall 2003
- Estimated Construction Completion: Winter 2006
Square Ft.: 104,000 gross sq. ft.
Project Team
Design Team: Diamond and Schmitt Architects
Construction Team: Skanska USA
Owner Team:
- Project Lead: Architecture, Engineering and Construction
- Support Units: