Project Data

Project Number: P100005309001

Budget: $49 million

Schedule:

  • Estimated Construction Start: Spring 2010
  • Estimated Construction Completion: Summer 2011

Square Ft.: 180,000 gross sq. ft.

 

Project Team

Design Team:

  • Integrated Design Solutions
  • Hanbury Evans Wright Vlattas

Construction Team: Walbridge Aldinger

Owner Team: