Project Number: P00010278
Budget: $90 million
Schedule:
- Construction Start: Spring 2018
- Construction Completed: February 2021
Square Feet:
- Renovation – 57,000 gross square feet
- New – 66,000 gross square feet
Design Team: SmithGroupJJR
Construction Team: Granger Construction Company