Project Number: P00004594
Budget: $116 million
Schedule:
- Estimated Construction Start: Winter 2012
- Estimated Construction Completion: Summer 2013
Square Ft.: 300,000 gross sq. ft.
Project Team
Design Team: Integrated Design Solutions
Construction Team: Walbridge Aldinger
Owner Team:
- Project Lead: Architecture, Engineering and Construction
- Support Units: