Project Number: P100014510002 (P00003880)
Budget: $29 million
Schedule:
- Estimated Construction Start: Summer 2012
- Estimated Construction Completion: Summer 2014
Square Ft.: 56,700 gross sq. ft. addition and 12,800 gross sq. ft. renovation
Project Team
Design Team: Lord Aeck & Sargent Incorporated
Construction Team: Barton Malow Company
Owner Team:
- Project Lead: Architecture, Engineering and Construction
- Support Units: