Project Number: P100524709002
Budget: $6 million
Schedule:
- Estimated Construction Start: Fall 2009
- Estimated Construction Completion: Fall 2010
Square Ft.: 20,000 gross sq. ft.
Project Team
Design Team: Jickling Lyman Powell Associates
Construction Team: O’Neal Construction Inc
Owner Team:
- Project Lead: Architecture, Engineering and Construction
- Support Units: