Project Data

Kresge Complex Demolition

Project Number: P100002020

Budget: $9.7 million

Schedule:

  • Estimated Construction Start: February 2010
  • Estimated Construction Completion: November 2010

Square Ft.: 260,000 gross sq. ft.

 

Project Team

Design Team: Smithgroup Incorporated

Construction Team: ONeal Construction Inc.

Owner Team: