Project Number: P100523608001
Budget: $5.5 million
Schedule:
- Estimated Construction Start: Fall 2008
- Estimated Construction Completion: Fall 2009
Square Ft.: 18,000 gross sq. ft.
Project Team
Design Team: Jickling Lyman Powell Associates Inc.
Construction Team: Phoenix Contractors, Inc.
Owner Team:
- Project Lead: Architecture, Engineering and Construction
- Support Units: