Project Data

MSRB II Chiller Replacement and Chilled Water Interconnection to Medical Sciences Research Building III

Project Number: P00008780

Budget: $14 million

Schedule:

  • Estimated Construction Start: Spring 2015
  • Estimated Construction Completion: Summer 2016

Project Team

Design Team: Integrated Design Solutions

Construction Team: Commercial Contracting Corporation