Project Number: P100511703001
Budget: $41 million
Schedule:
- Estimated Construction Start: October 2004
- Estimated Construction Completion: September 2006
Square Ft.: 112,500 gross sq. ft.
Project Team
Design Team: Albert Kahn Associates
Construction Team: Devon Industrial Group
Owner Team:
- Project Lead: Architecture, Engineering and Construction
- Support Units: