Project Number: P00009334
Budget: $23.5 million
Schedule:
- Estimated Construction Start: Winter 2015
- Estimated Construction Completion: Spring 2016
Square Ft.: 24,500 gross sq. ft.
Project Team
Design Team: HKS Inc
Construction Team: AZ Shmina Incorporated
Owner Team:
- Project Lead: Architecture, Engineering and Construction
- Support Units: