Project Number: P00011193
Budget: $39 million
Schedule:
- Construction Start: Winter 2019
- Construction Completed: December 2020
Square Feet:
-
- Addition – 65,000 gross square feet
Design Team: Harley Ellis Devereaux
Construction Team: Commercial Contracting Corporation
Maps and Construction Logistics
Design
Perspective from Mill Street & Circle Drive
News
Expanded Murchie Science Building opens at UM-Flint
February 3, 2021
Regents Approve Design for Murchie Expansion
December 7, 2017
UM-Flint to Expand Murchie Science Building
September 15, 2016