Central Power Plant 13,200 Volt Switchgear Upgrade

Project Number: P00012681

Budget: $23 million

Schedule:

  • Construction Start: Fall 2019
  • Construction Completed: October 2021

Square Feet: N/A

Design Team: Black & Veatch

Construction Team: Walbridge Aldinger

 