Project Data

Project Number: P1000177-99-002

Budget: $38.6 million

Schedule:

  • Construction Start: May 2002
  • Construction Completion: January 2004

Square Ft.: 139,800 gross sq. ft.

 

Project Team

Architect & Engineer:

  • Albert Kahn Associates, Inc., Project Architects & Engineers
  • Quinn Evans/Architects, Historic Preservation Architects
  • Kirkegaard Associates, Acoustic Consultants
  • Fisher Dachs Associates, Theatre Planning & Design
  • Gary Steffy Lighting Design, Lighting Consultants
  • Cummins & Barnard, Inc., Consultant Engineers

Construction Team: The Christman Company, Construction Manager

Major Subcontractors: 

  • John Darr Mechanical
  • Newkirk Electric Associates
  • Spence Brothers Concrete
  • Ann Arbor Ceiling and Partition (plaster/drywall)
  • CBN Steel Construction
  • Irwin Seating Company
  • Kulbacki, Inc. (carpentry/millwork)

Owner Team: