| October 2024 |
Nichols Drive Slope Stabilization (opens in new tab) |
Approval to Proceed with Project |
| December 2022 |
Bonisteel Boulevard Water Main and Road Reconstruction (opens in new tab) |
Approval to Proceed with Project |
| September 2019 |
Medical Campus Utility Infrastructure Upgrades (opens in new tab) |
Approval to Proceed with Project |
| September 2019 |
South University Pavement and Utility Improvements (opens in new tab) |
Approval to Proceed with Project |
| May 2019 |
Catherine Street Area Utility Infrastructure Upgrades (opens in new tab) |
Approval to Proceed with Project |
| February 2019 |
Bonisteel Boulevard Water Main and Road Reconstruction (opens in new tab) |
Approval to Proceed with Project |
| December 2017 |
Central Campus Storm Water Infiltration System (opens in new tab) |
Approval to Proceed with Project |
| July 2017 |
Michigan Medicine M29 Parking Lot Slope and Stair Improvements (opens in new tab) |
Approval to Proceed with Project |
| April 2017 |
Parking Lot NC92 Reconstruction and Ring Road Modifications (opens in new tab) |
Approval to Proceed with Project |
| March 2016 |
'42E Plaza Improvements (opens in new tab) |
Approval to Proceed with Project |
| March 2015 |
Eda U. Gerstacker Grove (opens in new tab) |
Approval of Schematic Design and Authorization to Issue the Project for Bids and
Award Construction Contracts |
| March 2015 |
Eda U. Gerstacker Grove (opens in new tab) |
Approval of Schematic Design and Authorization to Issue the Project for Bids and
Award Construction Contracts |
| December 2014 |
North Campus Grove Naming (opens in new tab) |
Authorization to name the North Campus Grove in honor of Eda U. Gerstacker |
| April 2014 |
North Campus Grove (opens in new tab) |
Approval of Project and Authorization to Appoint an Architect |
| April 2014 |
North Campus Grove (opens in new tab) |
Approval of Project and Authorization to Appoint an Architect |
| May 2013 |
Wilpon Baseball and Softball Complex Site Improvements (opens in new tab) |
Approval to Proceed with Project |
| November 2012 |
Central Campus Area Utility Tunnel Replacement (opens in new tab) |
Approval to Proceed with Project |
| May 2011 |
Beal Avenue Water Main and North Campus Storm Relief System Upgrades (opens in new tab) |
Approval to Proceed with Project |
| January 2011 |
Central Campus Area Utility Tunnel Refurbishment (opens in new tab) |
Approval to Proceed with Project |
| February 2010 |
Central Campus Transit Center (opens in new tab) |
Approval to Proceed with Project |
| February 2009 |
Central Campus Area 2009 Utility Tunnel and Piping Replacement (opens in new tab) |
Approval to Proceed with Project |
| December 2008 |
Intercollegiate Athletics Soccer Fields (opens in new tab) |
Approval of Revised Project Scope and Budget |
| May 2008 |
University of Michigan - Flint Kearsley Street Extension (opens in new tab) |
Approval to Proceed with Project |
| January 2008 |
Central Campus Area 2008 Utility Tunnel Replacements (opens in new tab) |
Approval to Proceed with Project |
| October 2007 |
Central Campus Area Utility Tunnel Replacement 2007 (opens in new tab) |
Approval to Proceed with Project |
| July 2007 |
Intercollegiate Athletics Soccer Fields (opens in new tab) |
Approval of Schematic Design and Authorization to Issue the Project for Bids and Award Construction Contracts |
| June 2007 |
Ingalls Substation to Wall Street Utility Duct Bank (opens in new tab) |
Approval to Proceed with Project |
| April 2007 |
Intercollegiate Athletics Soccer Fields (opens in new tab) |
Approval of Project and Authorization to Appoint an Architect |
| April 2007 |
North Campus Underground Chilled Water Lines Extension (opens in new tab) |
Approval to Proceed with Project |
| November 2006 |
Central Campus Area Utility Tunnel Replacement (opens in new tab) |
Approval to Proceed with Project |
| June 2006 |
Central Campus Area Utility Tunnel Replacement (opens in new tab) |
Approval to Proceed with Project |
| April 2005 |
South Campus Power and Telecommunication Duct Extensions (opens in new tab) |
Approval to Proceed with Project |
| April 2005 |
Washington Street Utility Upgrade (opens in new tab) |
Approval to Proceed with Project |
| March 2005 |
Chemistry Building Area Tunnel and Chamber Replacement (opens in new tab) |
Approval to Proceed with Project |
| February 2005 |
Central Campus South Steam Line (opens in new tab) |
Approval to Proceed with Project |
| February 2005 |
East Huron Street at Glen Avenue Parcels for Roadway Improvements (opens in new tab) |
Approval to Transfer Ownership of Real Estate |
| July 2004 |
Utility Tunnel Piping Project Central Power Plant to Victor Vaughn (opens in new tab) |
Approval to Proceed with Project |
| April 2004 |
North Campus Diag Stormwater Control (opens in new tab) |
Approval to Proceed with Project |
| April 2004 |
WVGR Radio Tower Project (opens in new tab) |
Approval to Proceed with Project |
| February 2004 |
Palmer Field Reconstruct Eight Tennis Courts (opens in new tab) |
Approval to Proceed with Project |
| May 2003 |
North Campus Stormwater Control and Detention Pond (opens in new tab) |
Approval to Proceed with Project |
| May 2003 |
Tunnels - POR 108 to 300 N. Ingalls Replace Underground Utilities to 300 North Ingalls (opens in new tab) |
Approval to Proceed with Project |
| October 2002 |
Tunnels - Upjohn to University Hospital Replace DHWS, DHWR and LPC Piping (opens in new tab) |
Approval to Proceed with Project |
| April 2002 |
Central Power Plant South End Tunnel Services Interface Modifications (opens in new tab) |
Approval to Proceed with Project |
| March 2002 |
Campus Communications Infrastructure Replacement/Expansion North Campus to East Campus Communications Connector at Arbor Lakes (opens in new tab) |
Approval to Proceed with Project |
| February 2002 |
Central Heating Plant Tunnels Repair Tunnel Chamber (opens in new tab) |
Approval to Proceed with Project |
| February 2002 |
Central Heating Plant Tunnels Repair Tunnel Chamber (opens in new tab) |
Approval to Proceed with Project |
| December 2001 |
Palmer Drive Development Pedestrian Bridge over Washtenaw Avenue (opens in new tab) |
Approval to Proceed with Project |
| December 2001 |
Replacement of Tunnel and Associated Utilities Located Between Hill Auditorium and Edward H. Kraus Building (opens in new tab) |
Approval to Proceed with Project |
| December 2001 |
Replacement of Tunnel and Associated Utilities Located Between Hill Auditorium and Edward H. Kraus Building (opens in new tab) |
Approval to Proceed with Project |
| December 2001 |
University of Michigan Hospitals and Health Centers (UMHHC) East Medical Center Drive Road-Widening Project (opens in new tab) |
Approval to Proceed with Project |
| April 2001 |
Land Improvements Fiber Optic Infrastructure (opens in new tab) |
Approval to Proceed with Project |
| February 2000 |
Underground Tunnel and Utility Replacement and Relocations (opens in new tab) |
Approval to Proceed with Project |
| February 2000 |
Underground Tunnel and Utility Replacement and Relocations (opens in new tab) |
Approval to Proceed with Project |
| October 1999 |
Replacement of Tunnel and Associated Utilities Located Under State Street near the Michigan Union (opens in new tab) |
Approval to Proceed with Project |
| February 1999 |
North Campus Road Repairs (opens in new tab) |
Approval to Proceed with Project |
| December 1998 |
Ruthven Museum to Central Campus Recreation Building Replacement of Tunnel Piping (opens in new tab) |
Approval to Proceed with Project |