Regents Action Items

Regents Action Items (1998 to Current)

MULTIPLE BLOCKS - 0000001

DateAgenda ItemAction
October 2024 Nichols Drive Slope Stabilization Approval to Proceed with Project
December 2022 Bonisteel Boulevard Water Main and Road Reconstruction Approval to Proceed with Project
September 2019 Medical Campus Utility Infrastructure Upgrades Approval to Proceed with Project
September 2019 South University Pavement and Utility Improvements Approval to Proceed with Project
May 2019 Catherine Street Area Utility Infrastructure Upgrades Approval to Proceed with Project
February 2019 Bonisteel Boulevard Water Main and Road Reconstruction Approval to Proceed with Project
December 2017 Central Campus Storm Water Infiltration System Approval to Proceed with Project
July 2017 Michigan Medicine M29 Parking Lot Slope and Stair Improvements Approval to Proceed with Project
April 2017 Parking Lot NC92 Reconstruction and Ring Road Modifications Approval to Proceed with Project
March 2016 '42E Plaza Improvements Approval to Proceed with Project
March 2015 Eda U. Gerstacker Grove Approval of Schematic Design and Authorization to Issue the Project for Bids and Award Construction Contracts
March 2015 Eda U. Gerstacker Grove Approval of Schematic Design and Authorization to Issue the Project for Bids and Award Construction Contracts
December 2014 North Campus Grove Naming Authorization to name the North Campus Grove in honor of Eda U. Gerstacker
April 2014 North Campus Grove Approval of Project and Authorization to Appoint an Architect
April 2014 North Campus Grove Approval of Project and Authorization to Appoint an Architect
May 2013 Wilpon Baseball and Softball Complex Site Improvements Approval to Proceed with Project
November 2012 Central Campus Area Utility Tunnel Replacement Approval to Proceed with Project
May 2011 Beal Avenue Water Main and North Campus Storm Relief System Upgrades Approval to Proceed with Project
January 2011 Central Campus Area Utility Tunnel Refurbishment Approval to Proceed with Project
February 2010 Central Campus Transit Center Approval to Proceed with Project
February 2009 Central Campus Area 2009 Utility Tunnel and Piping Replacement Approval to Proceed with Project
December 2008 Intercollegiate Athletics Soccer Fields Approval of Revised Project Scope and Budget
May 2008 University of Michigan - Flint Kearsley Street Extension Approval to Proceed with Project
January 2008 Central Campus Area 2008 Utility Tunnel Replacements Approval to Proceed with Project
October 2007 Central Campus Area Utility Tunnel Replacement 2007 Approval to Proceed with Project
July 2007 Intercollegiate Athletics Soccer Fields Approval of Schematic Design and Authorization to Issue the Project for Bids and Award Construction Contracts
June 2007 Ingalls Substation to Wall Street Utility Duct Bank Approval to Proceed with Project
April 2007 North Campus Underground Chilled Water Lines Extension Approval to Proceed with Project
April 2007 Intercollegiate Athletics Soccer Fields Approval of Project and Authorization to Appoint an Architect
November 2006 Central Campus Area Utility Tunnel Replacement Approval to Proceed with Project
June 2006 Central Campus Area Utility Tunnel Replacement Approval to Proceed with Project
April 2005 South Campus Power and Telecommunication Duct Extensions Approval to Proceed with Project
April 2005 Washington Street Utility Upgrade Approval to Proceed with Project
March 2005 Chemistry Building Area Tunnel and Chamber Replacement Approval to Proceed with Project
February 2005 Central Campus South Steam Line Approval to Proceed with Project
February 2005 East Huron Street at Glen Avenue Parcels for Roadway Improvements Approval to Transfer Ownership of Real Estate
July 2004 Utility Tunnel Piping Project Central Power Plant to Victor Vaughn Approval to Proceed with Project
April 2004 North Campus Diag Stormwater Control Approval to Proceed with Project
April 2004 WVGR Radio Tower Project Approval to Proceed with Project
February 2004 Palmer Field Reconstruct Eight Tennis Courts Approval to Proceed with Project
May 2003 North Campus Stormwater Control and Detention Pond Approval to Proceed with Project
May 2003 Tunnels - POR 108 to 300 N. Ingalls Replace Underground Utilities to 300 North Ingalls Approval to Proceed with Project
October 2002 Tunnels - Upjohn to University Hospital Replace DHWS, DHWR and LPC Piping Approval to Proceed with Project
April 2002 Central Power Plant South End Tunnel Services Interface Modifications Approval to Proceed with Project
March 2002 Campus Communications Infrastructure Replacement/Expansion North Campus to East Campus Communications Connector at Arbor Lakes Approval to Proceed with Project
February 2002 Central Heating Plant Tunnels Repair Tunnel Chamber Approval to Proceed with Project
February 2002 Central Heating Plant Tunnels Repair Tunnel Chamber Approval to Proceed with Project
December 2001 Palmer Drive Development Pedestrian Bridge over Washtenaw Avenue Approval to Proceed with Project
December 2001 Replacement of Tunnel and Associated Utilities Located Between Hill Auditorium and Edward H. Kraus Building Approval to Proceed with Project
December 2001 Replacement of Tunnel and Associated Utilities Located Between Hill Auditorium and Edward H. Kraus Building Approval to Proceed with Project
December 2001 University of Michigan Hospitals and Health Centers (UMHHC) East Medical Center Drive Road-Widening Project Approval to Proceed with Project
April 2001 Land Improvements Fiber Optic Infrastructure Approval to Proceed with Project
February 2000 Underground Tunnel and Utility Replacement and Relocations Approval to Proceed with Project
February 2000 Underground Tunnel and Utility Replacement and Relocations Approval to Proceed with Project
October 1999 Replacement of Tunnel and Associated Utilities Located Under State Street near the Michigan Union Approval to Proceed with Project
February 1999 North Campus Road Repairs Approval to Proceed with Project
December 1998 Ruthven Museum to Central Campus Recreation Building Replacement of Tunnel Piping Approval to Proceed with Project
Skip to content