Regents Action Items

Regents Action Items (1998 to Current)

MULTIPLE BUILDINGS - 1080002

DateAgenda ItemAction
March 2023 Recreational Sports Fields Hubbard Road, North Campus Approval to Proceed with Project
February 2023 University of Michigan Recreational Sports Fields Hubbard Road, North Campus Approval to Proceed with Project
September 2022 Environmental and Water Resources Engineering Building and George Granger Brown Memorial Laboratories Civil and Environmental Engineering Project Approval to Proceed with Project
July 2021 Medical Science Research Buildings I, II, and III Installation of Back Up Generators Approval to Proceed with Project
July 2021 William W. Cook Legal Research Library and Hutchins Hall Exterior Repairs Approval to Proceed with Project
December 2020 Carl A. Gerstacker Building Herbert H. Dow Building Center for Ultrafast Optical Science Expansion Approval to Proceed with Project
December 2020 Carl A. Gerstacker Building Herbert H. Dow Building Center for Ultrafast Optical Science Expansion Approval to Proceed with Project
March 2018 Stephen M. Ross School of Business Exterior Completion Approval to Proceed with Project
February 2018 Camp Davis Rocky Mountain Field Station Student Cabin and Support Facilities Replacement Approval to Proceed with Project
December 2017 Michigan Medicine East Ann Arbor Health and Geriatrics Center Infrastructure Upgrades Approval to Proceed with Project
September 2017 North Campus Research Complex Buildings 20 and 25 Laboratory Renovation - Issue the Project for Bids and Award Construction Contracts Item for Information
May 2017 North Campus Research Complex Buildings 20 and 25 Laboratory Renovation Approval of Schematic Design
October 2016 North Campus Research Complex Buildings 20 and 25 Laboratory Renovation Approval of Project and Authorization to Appoint an Architect
September 2016 North Campus Research Complex Buildings 40 and 50 Demolition Approval to Proceed with Project
September 2016 University of Michigan Hospitals and Health Centers Multiple Buildings Pneumatic Tube System Communication Network Upgrade Approval to Proceed with Project
May 2016 University of Michigan Hospitals and Health Centers North Campus Research Complex Buildings 30, 35, 36, and 60, University Hospital, and University Hospital South Clinical Pathology Laboratories Relocation and Renovation Authorization to Issue the Project for Bids and Award Construction Contracts
December 2015 Stephen M. Ross Athletic Campus Athletics South Competition and Performance Project Authorization to Issue the Project for Bids and Award Construction Contracts
December 2015 University of Michigan Hospitals and Health Centers North Campus Research Complex Buildings 30, 35, 36, and 60, University Hospital, and University Hospital South Clinical Pathology Laboratories Relocation and Renovation Approval Schematic Design
November 2015 University of Michigan Hospitals and Health Centers University Hospital Fire Detection and Alarm System Update Approval to Proceed with Project
November 2015 University of Michigan Hospitals and Health Centers University Hospital South Electroconvulsive Therapy Relocation Approval to Proceed with Project
May 2015 Stephen M. Ross Athletic Campus Athletics South Competition and Performance Project Approval of Schematic Design and Authorization to Issue Bids and Award Construction Contracts for Early Procurement Packages
April 2015 University of Michigan Hospitals and Health Centers North Campus Research Complex Buildings 30, 35, 36, and 60, University Hospital, and University Hospital South Clinical Pathology Laboratories Relocation and Renovation Approval of Project and Authorization to Appoint an Architect
February 2015 Medical Sciences Research Building II Chiller Replacement and Chilled Water Interconnection to Medical Sciences Research Building III Approval to Proceed with Project
February 2015 Medical Sciences Research Building II Chiller Replacement and Chilled Water Interconnection to Medical Sciences Research Building III Approval to Proceed with Project
February 2015 Medical Sciences Research Building II Chiller Replacement and Chilled Water Interconnection to Medical Sciences Research Building III Approval to Proceed with Project
February 2015 Stephen M. Ross Athletic Campus Athletics South Competition and Performance Project Authorization to Issue Bids and Award Limited Construction Contracts for Abatement, Building Demolition, and Site Clearing
September 2014 Stephen M. Ross Athletic Campus Athletics South Competition and Performance Project Approval of Project and Authorization to Appoint an Architect
May 2014 North Campus Research Complex Buildings 10 and 14 Renovations for the Institute for Healthcare Policy and Innovation Approval to Proceed with Project
April 2014 Dental Building to Palmer Commons Chilled Water Interconnection Approval to Proceed with Project
December 2013 Harlan Hatcher Graduate Library Life Safety Upgrades Approval to Proceed with Project
October 2013 Stephen M. Ross Athletic Campus Naming Authorization to name the Stephen M. Ross Athletic Campus
January 2012 Northwood Apartments I, II, and III Fire Alarm and Boiler Upgrades Approval to Proceed with Project
November 2011 Vera B. Baits Houses II Renewal Approval to Proceed with Project
April 2010 University of Michigan Hospitals and Health Centers Multiple Buildings Pneumatic Tube System Upgrade Approval to Proceed with Project
December 2009 North Campus Research Complex Buildings 100, 200, 300 and 400 Interior Renewal Approval to Proceed with Project
September 2009 Building Access Control Project Approval to Proceed with Project
June 2009 Kresge Complex Demolition Approval to Proceed with Project
July 2008 Camp Davis Rocky Mountain Field Station Cabin Replacement and Infrastructure Improvement Approval to Proceed with Project
September 2005 Oxford Housing Fire Alarm System Upgrade and Fire Suppression System Installation Approval to Proceed with Project
February 2005 Engineering Research Buildings I & II, Gerstacker Building, and School of Information North Building Boiler Replacement Approval to Proceed with Project
February 2005 Harlan Hatcher Graduate Library Central Chiller Plant and Substation Replacement Approval to Proceed with Project
September 2004 University of Michigan Hospitals and Health Centers (UMHHC) Chilled Water Loop Replacement Phase I Approval to Proceed with Project
September 2004 University of Michigan Hospitals and Health Centers (UMHHC) Multiple Buildings - Bulk Oxygen System Approval to Proceed with Project
April 2002 Fletcher Parking Deck Elevated Connection to Palmer Drive Development Approval to Proceed with Project
April 2002 Undergraduate Science Instruction Center Approval of Schematic Design
December 2001 Palmer Drive Development Elevated Pedestrian Walkway adjacent to the Science Instruction Center Approval to Proceed with Project
December 2001 Palmer Drive Development Pedestrian Bridge over Washtenaw Avenue Approval to Proceed with Project
June 2001 Palmer Drive Development Elevated Pedestrian Walkways and Lighting for Palmer Drive Approval to Proceed with Project
June 2001 Medical School Temporary Animal Facilities and Demolition of the Neuroscience Building Approval to Proceed with Project
June 2001 Modern Language Building, Hill Auditorium, Burton Tower Chiller and Electrical Substation Upgrade Approval to Proceed with Project
April 2001 Gordon Hall, Village of Dexter Item for Information
March 2001 Northwood IV Exterior Siding Repair and Stain Approval to Proceed with Project
February 2001 Walgreen Drama Center Authorization to Appoint an Architect
November 2000 Palmer Drive Central Chillers Approval to Proceed with Project
May 2000 The University of Michigan Walgreen Drama Center Approval of Project and Site The University of Michigan Walgreen Drama Center Approval of Project and Site
March 2000 East University Plaza Area/Palmer Drive Storm Water Remediation Approval to Proceed with Project
March 2000 Medical Science II and Buhl Center for Human Genetics Buildings Renovation Project Phase II Approval to Proceed with Project (Approval to Put Out for Contractual Bid)
February 2000 Medical Science II and Buhl Center for Human Genetics Buildings Renovation Project Phase II Approval of Project and Authorization to Appoint an Architect
October 1999 Mason Hall and Haven Hall Renovation Project Approval of Revised Project and Approval of Design
July 1999 Life Sciences Institute Building Project and Palmer Drive Parking Structure Project Approval of Projects, Site, and Architects
July 1999 Medical Science Buildings 1 and 2 Renovations for Bioinformatics Approval to Proceed with Project
November 1998 Medical Science II and Buhl Center for Human Genetics Buildings Renovation Project Approval to Proceed with Project
Skip to content