4.0 Special Instructions to Designers

Guideline Last Update Previous Version Replaces Document
4.1 Compatibility with Existing Conditions May 2014 December 1991 SID-C Compatibility with Existing Conditions
4.2 Building Envelope August 2014 May 2014 SID-A Building Envelope
4.3 Building Commissioning July 2016 April 2016 SID-G Commissioning
4.3.1 Design Phase Commissioning November 2016 October 2012  
4.3.2 MEP Design Management November 2016 October 2012  
4.3.3 Full Construction-Phase Commissioning September 2018  July 2016  
4.3.4 Reduced Scope Construction Phase June 2018  July 2016  
4.3.5 Commissioning Plan Procedure June 2018 July 2016  
4.3.6 General Commissioning Procedures September 2018 June 2018   
4.4 Site/Civil      
4.4.1 Landscape December 2018 January 2017 SID-T Landscape Materials
4.4.2 Site Furnishing Standards Manual July 2018 January 2011  
4.4.3 Stormwater Best Management Practices Manual Removed January 2017 December 2010  
4.4.4 Banners      
4.4.5 Site Signage February 2016    
4.5 Regulated and Hazardous Materials July 2008 July 2006 SID-I Regulated and Hazardous Materials
4.6 Utilities for University Buildings May 2020 November 2015 SID-J University Provided Utilities
4.7 Building Access Control January 2021 March 2018 SID-Q Building Access Control
4.8 Fall Protection on Rooftops March 2025 June 2010 SID-R Fall Protection on Rooftops
4.9 Bird Collision Deterrence July 2023    
4.10 Telecommunication Cabling System November 2023